Due to the Technopark project, Karawang where using Industrial Floor Concrete would like to speed up their construction.
The owner contact me to ask the possibility and our capability to serve them if they will pour the concrete by 3 modules/day (maximum 2 modules in the same time then follow with the 3rd module after finished first 2 module)
Please appoint to have a meeting with contractor to plan for this matter because the contractor is quite not confident in our capacity to supply because currently they still face discontinuous delivery.
Therefore, please give the priority to this project while pouring concrete and prepare the no. of truck mixture sufficiently to avoid the quality problem on the floor construction.
Thank you for your attention and your effort to satisfy our customer requirement ya..